Running a steering committee that delivers decisions

In brief

A steering committee is the body where the people with authority over a project take, at regular dates, the decisions that exceed the project manager's delegation. Management Square proposes here a method for running a steering committee, in order: purpose and members, pack sent before the meeting, a running order centred on decisions, a record written during the meeting, follow-up until the next meeting.

Page contents

As a working convention, we call a steering committee here the body where the people with authority over a project take, at regular dates, the decisions that exceed the project manager’s delegation: scope, budget, committed deadlines, passing a milestone. Running a steering committee, in this sense, means conducting a cycle longer than the meeting itself.

Elsewhere, the same name refers to meetings with a different purpose, and each organisation sets its own. In the cycle described here, the purpose of the body and its members are written down once. Each meeting is then prepared through a pack sent in advance, follows the order of the decisions requested, closes with a record validated on the spot and continues with follow-up. The content of the review (actual progress, risks, passing a milestone) is the subject of our article on the project review. The steps that follow concern how the body is run, and we propose them as a method.

The purpose of the body is written down before the first meeting

A committee without a written purpose can take on anything: top-down information, coordination between teams, technical questions. The first step produces a page, which the sponsor signs. It states which decisions belong to the committee, which remain with the project manager, how often the body meets and who chairs it.

The boundary with the project manager is set by thresholds: a budget or schedule overrun beyond an agreed margin, a change of scope that affects an objective. These margins have a name in the PRINCE2 method, tolerances: a forecast overrun is escalated to the committee.

The same page separates the steering committee from neighbouring meetings. The progress meeting, sometimes called the project committee, coordinates the teams’ work and does not need the decision-makers. On a programme, a programme committee arbitrates between projects, according to the governance described in our page on programme management. Combining these purposes in a single meeting lengthens the agenda and can keep away those whose presence counts.

Around the table, people who can decide

The committee is made up of the people who can decide on what the purpose page entrusts to the body. We propose that it include the sponsor, a representative of those who will use the result and a representative of those who build it, in-house or at a supplier: in the vocabulary of IT projects, the project owner and the project contractor. Experts attend by invitation, for the item that concerns them.

Chairing and facilitating are two roles. The sponsor chairs: they decide, or note the members’ agreement. Facilitation falls to the project manager or, where the project has one, to its PMO: preparing the pack, keeping to the agenda, wording the decisions, writing the record.

Absence is settled in advance. A member who cannot attend appoints a deputy holding a written delegation. A deputy without delegation can only listen: the decisions that depended on the member are then withdrawn from the agenda and follow a written circuit, outside the meeting.

A pack read before entering the meeting

The pack goes out a fixed time before the meeting, set in the purpose page: early enough to be read, late enough to be up to date. Its first page sets out the decisions requested. Each takes up a few lines: the question, the options, what each option costs in time, budget and scope, the project manager’s recommendation, and the date after which not deciding amounts to choosing.

The rest of the pack serves as evidence: milestone status, forecasts at completion, risks whose decision deadline is approaching, according to the sorting described in our article on project risk management.

Between sending the pack and the meeting, the facilitator talks to each member on whom a decision depends. They do not seek to obtain agreement. They check that the question is understood, collect objections and identify the missing information. A decision that its author discovers in the meeting may be postponed for that reason alone.

If the pack is not ready on the sending date, the sponsor chooses between a meeting with a reduced agenda and a postponed meeting.

Running a steering committee, decision after decision

The meeting follows a fixed order. It opens with the previous record: each decision that has fallen due is declared applied, late or abandoned, without reopening the substantive debate. Next come the decisions requested, from the heaviest to the lightest, while all the decision-makers are present. Information, progress status included, comes last and is limited to questions on the pack.

For each decision, the facilitator proceeds in the same way. They recall the question and the options, give the floor to the project manager for their recommendation, then to the members. Before moving to the next item, they restate aloud what has just been decided, name the owner and the deadline, and wait for the chair’s agreement. This restatement is the moment when a disagreement that has remained implicit can come out.

An item closes with one of these outcomes: decided; postponed, with the missing information and the person who will provide it; or referred to another body, which the facilitator names. As long as none has been pronounced, the item remains open.

The facilitator also keeps time. A technical discussion that settles in is referred to a workshop, with a date and a rapporteur. A subject brought up in the meeting, outside the pack, is placed on the next meeting’s agenda, unless the chair recognises it as urgent.

The decision record is written during the meeting

The record contains what the meeting produced, without recounting the discussions. It is organised in sections: decisions, postponements, actions. Each decision is written in one sentence that can be understood without having attended the meeting, with its owner, its deadline and, where relevant, the option set aside.

Written as the meeting goes along, then projected or read back before closing, it is validated by the chair in front of the members. This on-the-spot validation avoids a review circuit, which can delay circulation and reopen debates. We propose sending the record the same day or the next, to the members and to the people responsible for an action, including those who were not present.

A wording is checked by putting yourself in the position of the person designated: the line that concerns them must tell them, on its own, what they will have done and by what date. “Look into the schedule question” does not meet this condition. “The project manager presents two cutover scenarios, with their cost, at the next committee” does.

The decisions from all the records feed a single register, kept by the facilitator: number, date, wording, owner, deadline, status.

Between two committees, following up decisions

Follow-up starts the day after the meeting. The facilitator chases the owners before the deadline, without waiting for the next committee. When a decision runs into an obstacle, they flag it to the sponsor, so that it is maintained, modified or lifted by the person who took it.

Some decisions cannot wait for the next meeting. The purpose page provides a short circuit for them: a one-page note sent to the members, a written answer from the chair within an announced time, then entry in the register.

The register provides measures of the body: the share of decisions that have fallen due and been applied, and the time between a request being entered and the decision. Their conventions are set out in our article on PMO KPIs. When several projects run their committees according to this cycle, a common pack and record format makes their decisions comparable: this is one of the purposes of setting up a PMO.

When the records of several consecutive meetings contain only information, the facilitator says so to the sponsor and proposes reviewing the frequency or the purpose of the body.

Insights

Further reading

All insights
HRIS change management put to the test by a deployment that employees work around

HRIS change management brings together the actions that lead employees, managers and HR administrators to carry out their human resources transactions in the new system, and to leave the previous channels. Management Square describes here what makes an HRIS falter after go-live (payroll, personal data, workload shifted onto managers, staff representatives) and the order in which to remedy it.

Read the analysis
From project PMO to agile PMO, a change of stance

Common usage calls an agile PMO a project office serving teams that deliver in iterations: it plans a cadence and a capacity, measures what is delivered and prepares priority arbitrations, without changing its mandate. Management Square compares here this stance with that of a project PMO in a predictive life cycle: what the office plans, measures, has arbitrated and stops doing, then what it keeps.

Read the analysis
Agile story mapping: how a workshop unfolds, card after card

Agile story mapping is a workshop technique, attributed to Jeff Patton, that arranges a product's user stories along two axes: the user's journey from left to right, necessity from top to bottom. Management Square describes here how it unfolds, step by step: the people to bring together, the map built on the wall and the release plan that comes out of it.

Read the analysis

FAQ

Frequently asked questions

Another question? Ask us

Who runs a steering committee?

In the allocation we propose, the sponsor chairs the steering committee and decides there, while facilitation falls to the project manager or the project's PMO. The facilitator prepares the pack, keeps to the agenda, restates each decision and writes the record. When they also present the status of their own project, they benefit from handing the record and timekeeping to another person.

How do you prepare a steering committee?

In the method we propose, a steering committee is prepared through a pack sent a fixed time before the meeting, whose first page lists the decisions requested: the question, the options, the consequences of each, the recommendation and the deadline. Between sending the pack and the meeting, the facilitator talks to the members on whom a decision depends, to check that the question is understood and to identify the missing information.

What does a steering committee decision record contain?

The decision record contains what the meeting produced: the decisions taken, the items postponed with the information expected, and the actions. Each line carries an owner and a deadline, and can be understood without having attended the meeting. The record does not recount the discussions. We propose having it validated by the chair before the meeting closes, then circulating it the same day or the next.

What should you do when a decision-maker is absent from the steering committee?

We propose setting the rule in advance, in the page that describes the body. A member who cannot attend appoints a deputy holding a written delegation on the agenda items. Failing that, the decisions that depend on them are withdrawn from the meeting and handled through a written circuit, with an answer expected by an announced date, then entered in the decision register.

Does every project need a steering committee?

Not necessarily. The body is justified when decisions involve several departments or go beyond what one sponsor can decide alone. For a short project where a single person owns the budget and the result, a regular check-in between that sponsor and the project manager, closed with a written record, fulfils the same function. The same rules apply: decisions requested in advance, worded in writing, then followed up.