The difference between a programme and a project, then the criteria that justify a programme

In brief

The difference between a programme and a project lies, in common usage, in what is accounted for: a project delivers a defined result, a programme brings together linked projects to obtain a benefit that none would produce alone. Management Square proposes here four criteria for deciding to set up a programme (common benefit, dependencies, shared resources, duration) and details the price of this choice.

Page contents

A project and a programme are distinguished by what is being led, whatever their size. In common usage, the word project refers to a time-bound effort, carried out to deliver a defined result: an application put into service, a site opened, an organisation put in place. The word programme refers to a set of linked projects, brought together under a single leadership to obtain a benefit beyond the reach of each one taken in isolation. The difference between a programme and a project therefore lies in what is accounted for: one delivery in the first case, the effect of several deliveries in the second.

These working definitions do not reproduce the text of any standard. They are enough to frame the choice that matters to senior management: run several projects separately, or bring them together into a programme. We propose to settle it on four criteria (a common benefit, dependencies, shared resources, duration), then to weigh up the price of a programme, in structure and in decision-making delays. Set up without a common benefit, a programme adds a layer of management to projects that did not need one.

The difference between a programme and a project, and the place of the portfolio

A project manager accounts for a delivery, on the agreed date and at the agreed cost. A programme director accounts for an effect, which the deliveries must produce together. Each project keeps its manager, its plan and its budget. The programme carries what lies between them: the order of go-lives, the commitments of one project to another, the trade-offs, the preparation of the teams who will receive the result.

We propose a test to place a set of projects. If one of them is removed, do the others keep their reason for being? If so, the set is a list. When removing a single one deprives the others of their usefulness, the set is run as a whole.

The portfolio is a third object. It brings together projects and programmes, linked or not, because they draw on the same budget and the same teams, and it is used to choose those the organisation commits to. Our entry on PPM gives its vocabulary. Our page on programme management sets the three levels side by side in a table.

The word “programme” can also name a large project, or a department’s budget line. The former remains a project as long as it has a team, a plan and a delivery; the latter is a share of the portfolio. The Project Management Institute awards a separate credential for project, programme and portfolio, as presented in our entry on PMI certifications.

The criteria that justify setting up a programme

The table presents these criteria in the order in which we propose to examine them; the grid is adjusted to each organisation.

Criterion What to look at Argues for a programme Argues for separate projects
Common benefit The result expected by senior management, and the person who promised it A result that no project produces alone, carried by a single sponsor An investment case and a benefit specific to each project
Dependencies The deliveries of one project that another needs Cross dependencies, renewed at each stage An isolated, one-way dependency, dated once
Shared resources Scarce skills, key users, cutover periods The same people called on by several projects for the same result Separate teams, or sharing that the portfolio already arbitrates
Duration The horizon of the result and the number of go-lives A long horizon, divided into stages that each call for a decision Short projects, delivered once

In this grid, the criteria do not carry the same weight. The common benefit is the condition: without it, a programme director has nothing to account for, and the other criteria merely describe projects that get in each other’s way. Dependencies then say whether this benefit is exposed. The more they cross, the more a delay spreads without any project manager having the authority to arbitrate.

Shared resources, on their own, do not make a programme. Two unrelated projects competing for the same architect raise a question of capacity, and this is settled at the level where the organisation orders all its projects: this is the purpose of project portfolio management. Duration, finally, acts as a threshold. A programme requires a set-up (mandate, governance bodies, programme office) that only pays off if the whole lasts long enough to use it.

Suppose a haulier wants to merge two warehouse networks after an acquisition, and entrusts four project managers with the warehouse management system, the item master data, the transport plan and the reorganisation of the sites. None of these projects produces the unified network alone. The new system cannot open a site without the master data. The same operators are expected in acceptance testing by all four teams, and the sites cut over in waves. All four criteria are met.

A programme has a price, in structure and in decision-making delays

Setting up a programme adds a level between the projects and senior management: a programme director, a sponsor who devotes time to it, a body that arbitrates and, as soon as there are many projects, an office that holds the overall plan and the registers. Our article on the role and responsibilities of the PMO describes this office at programme level.

The price is also paid in the projects. Each project manager reports twice, to their sponsor and to the programme. They lose control of certain dates, which the programme sets for everyone. A decision that used to be taken between them and their management goes through one more body, and therefore one more delay if the delegation thresholds are not written down. This allocation is covered in our article on programme governance.

The absence of a programme also has a price when the criteria are met: nobody holds the order of go-lives or the commitments of one project to another. The choice therefore compares two costs, that of the structure and that of its absence.

When separate projects are enough, and when the programme exists without saying so

Several situations do without a programme:

  • projects that have nothing in common but a department or a budget envelope belong to the portfolio, which orders and arbitrates them;
  • a large project divided into work packages, with a single management team and a single go-live, remains a project, and its work packages are coordinated in its plan;
  • two projects linked by a single delivery make do with a written commitment between the two project managers, with a subject and a date of need.

The reverse situation exists: projects run separately form a programme that nobody has set up. Project managers negotiate dates among themselves without anyone able to decide between them. A benefit has been announced to senior management, and no project file carries it. A delay in one shifts the go-live of another, and senior management learns of it through the second.

The choice can be revised. Projects already launched can be brought together along the way, provided a sponsor is appointed and their mutual commitments are brought into an overall plan, described in our article on the master schedule. A programme can also hand its projects back to their departments on the day they no longer depend on one another.

The first criterion provides the starting point: ask the prospective sponsor to write down the common benefit and to name the person who will account for it after the last go-live. If they cannot, the projects remain projects, and their links are handled at portfolio level.

Insights

Further reading

All insights
The project business case, measures to keep up after the budget is approved

A project business case is the document that justifies an investment by setting what the project costs against what it should bring in, by when and with what uncertainty. Management Square proposes here to treat it as four measures (full cost, benefits by type, timing, risks), each entrusted to a person who keeps it up to date, and to review it at each decision point.

Read the analysis
In programme governance, who decides, at what level and on what information?

Programme governance refers to the rules that set who decides what in a programme, at what level, on what information and within what timescale. Management Square proposes here an allocation of decisions, following the questions of an executive committee about to fund a programme: inventory of decisions, delegation thresholds, information for the board, disputes between projects, closure.

Read the analysis
From project PMO to agile PMO, a change of stance

Common usage calls an agile PMO a project office serving teams that deliver in iterations: it plans a cadence and a capacity, measures what is delivered and prepares priority arbitrations, without changing its mandate. Management Square compares here this stance with that of a project PMO in a predictive life cycle: what the office plans, measures, has arbitrated and stops doing, then what it keeps.

Read the analysis

FAQ

Frequently asked questions

Another question? Ask us

What is the difference between a programme and a project?

In common usage, a project is a time-bound effort that delivers a defined result, led by a project manager. A programme brings together several linked projects to obtain an overall effect, for example a unified network or a new way of operating, led by a programme director who holds the order of go-lives, the dependencies and the trade-offs. The former is judged on its delivery, the latter on the effect obtained.

Does a large project become a programme?

No, in the usage described here. A project with a large budget and many work packages remains a project as long as a single management team leads a single plan towards one go-live. It is run as a programme when it is split into projects entrusted to separate managers, whose deliveries wait on one another to produce the result.

What is the difference between a programme and a project portfolio?

In common usage, the projects in a programme are linked: they contribute to the same benefit, and the programme ends when that benefit is obtained or abandoned. A portfolio brings together projects and programmes, linked or not, that are funded from the same envelope and call on the same teams. It is permanent and is used to choose what the organisation commits to.

Can projects already under way be brought together into a programme?

Yes, when these projects turn out to contribute to the same benefit and to depend on one another. We then propose three acts: appoint a sponsor and a programme director, bring the commitments between projects into an overall plan and tell the project managers what is now decided at programme level. Without them, the grouping risks changing nothing but the title.